Version vom 2. Februar 2025, 17:15 Uhr
Each building can be extended up to a size of 10,000m². A further 10,000 m² is added to the basic value per level. This upper limit is then lifted from level 5. However, an additional building permit is required every 20,000m².
For every 20m² of production area, 1 employee can be employed in a factory; in all other production buildings, 50m² is required. the production area must be at least as large as the storage area
Start warehouse slots: 3 (the factories 4)
- Slot expansion:
- maximum 10 warehouse slots + 5 per current level
- Price: old number of slots x 1000€
- Duration: old number of slots x 20h
Start production slots: 1
- Slot expansion:
- maximum 5 production slots + 2 per current level
- Price: old number of slots x 4000€
- Duration: old number of slots x 40h
- Attention: Please refer to the following section for the distribution of employees!
See also Employees#Work slots
The classification of the individual factory workers :
|
|
Agricultural building Level 0
|
- Employees: Rancher
- Extension costs: 100,-€ per m²
- Construction time & closed extension: 162sek per m² (4,5h per 100m²)
- Extension time with open building: 324sek per m² (9h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Farmer
- Extension costs: 100,-€ per m²
- Construction time & closed extension: 162sek per m² (4,5h per 100m²)
- Extension time with open building: 324sek per m² (9h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Farmer
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 162sek per m² (4,5h per 100m²)
- Extension time with open building: 324sek per m² (9h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Factory building Level 0
|
- Employees: Laborer
- Extension costs: 100,-€ per m²
- Construction time & closed extension: 324sek per m² (4,5h per 100m²)
- Extension time with open building: 648sek per m² (9h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
Endprodukte
Food
|
Fruit and vegetables
|
Drinks
|
Kiosk goods
|
Baked goods
|
Meat products
|
Drugstore articles
|
Zoo articles (Level 2)
|
Electrical goods
|
Flower store
|
Gas station
|
Intermediate products
|
Agricultural building Level 1
|
- Employees: Fisherman
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 162sek per m² (4,5h per 100m²)
- Extension time with open building: 324sek per m² (9h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Lumberjack
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 162sek per m² (4,5h per 100m²)
- Extension time with open building: 324sek per m² (9h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Mines Level 1
|
- Employees: Miner
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Miner
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Miner
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Factory building Level 1
|
- Employees: Worker
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Worker
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Worker
- Extension costs: 200,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Factory building Level 2
|
- Employees: Skilled worker
- Extension costs: 300,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Skilled worker
- Extension costs: 300,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Factory building Level 3
|
- Employees: Technician
- Extension costs: 400,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Technician
- Extension costs: 400,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Mines Level 4
|
- Employees: Miner
- Extension costs: 500,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Factory building Level 4
|
Hitech factory
|
- Employees: Engineer
- Extension costs: 600,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
- Employees: Engineer
- Extension costs: 500,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|
Factory building Level 5
|
Vehicle factory
|
- Employees: Engineer
- Extension costs: 500,-€ per m²
- Construction time & closed extension: 324sek per m² (9h per 100m²)
- Extension time with open building: 648sek per m² (18h per 100m²)
- Minimum building size: 50m² production area / 20m² warehouse
Products to be produced here:
|